Construction Updates

The Monon Corridor 101 page is live! View the page for service information and schedule.

Weeks of November 3 and November 10, 2025

On this page:

Global

Working Hours
  • Trackwork construction activities for the remainder of the project are ongoing and will take place from 6AM to 7PM.
Site Testing
  • Testing in Go Hammond and Town of Munster, Indiana on December 1st and 2nd during daytime hours. View Facebook Post.
  • Various testing activities throughout the eight-mile project area.

Hammond

Station Construction
  • Contractor finishing elevator inspection at Hammond Gateway Station.

Gate Crossing Loop Detector Installation and Testing
  • Working at Sheffield/SSL and Hohman/SSL week of 11/3/2025. Roadway flaggers will be controlling traffic through the grade crossing.
  • Working from Douglas to 173rd starting on 11/13/2025.
    • 165th Street
      • Work begins on 11/17 around 9PM through 11/18 5AM.
      • Work will be done under flagger protection.

Munster

Station Construction
  • Munster-Dyer West Access
    • Landscaping Activities
      • Trucking operations on Allison Road/Columbia Ave/Sheffield Ave. Minimal impacts to vehicular traffic.
    • Parking Lot Construction
      • Landscaping Activities
        • Trucking operations on Allison Road, minimal impacts to vehicular traffic.

Gate Crossing Loop Detector Installation and Testing
  • Working at Fisher Street and Ridge Road
    • Ridge Road work begins on 11/19 around 9PM through 11/20 5AM. Work will be done under flagger protection.

Dyer

Flatwork and Asphalt Paving
  • Finishing emergency access roads
    • Removal of material, pouring of new curb and sidewalk, asphalt installation and bollard installation.
    • Trucking operations on Main Street, minimal impacts to vehicular traffic.

For additional information about work in your area, please contact 219.296.6004.

Environmental Commitments
NICTD has committed to specific mitigation measures that are intended to reduce the adverse effects of NICTD's West Lake Corridor Project. The information below summarizes the mitigation measures that the FTA and NICTD committed to in the 2018 Final Environmental Impact Statement / Record of Decision. View the progress and status of each environmental commitment .